City of Bothell Downtown Cleanup and Redevelopment
Client: City of Bothell
Overview of Floyd|Snider Contributions
Project Summary
Floyd|Snider currently supports the City of Bothell (City) at four cleanup sites at different stages of the regulatory cleanup process.
At a former bus barn site with leaking petroleum storage tanks, Floyd|Snider facilitated completion of a site-wide cleanup after multiple prior rounds of interim soil excavations. The site received a No Further Action determination following remediation.
At one former dry cleaner site, Floyd|Snider facilitated targeted data gaps investigation and Ecology approval of a RI/FS and Cleanup Action Plan. Cleanup construction is currently in progress.
At another former dry cleaner site, Floyd|Snider took over management of the existing remediation system to optimize performance, which helped to quickly reduce the mass of dissolved chlorinated volatile organic compounds and shorten the projected time frame for achievement of cleanup levels.
At a former machine shop site, Floyd|Snider assisted the City with reassessing a planned cleanup action with targeted supplemental data collection, resulting in a revised cleanup approach with lower cost and reduced impacts to public space that is equally protective of human health and the environment.
Floyd|Snider currently supports the City of Bothell (City) at four cleanup sites at different stages of the regulatory cleanup process.
At a former bus barn site with leaking petroleum storage tanks, Floyd|Snider facilitated completion of a site-wide cleanup after multiple prior rounds of interim soil excavations. The site received a No Further Action determination following remediation.
At one former dry cleaner site, Floyd|Snider facilitated targeted data gaps investigation and Ecology approval of a RI/FS and Cleanup Action Plan. Cleanup construction is currently in progress.
At another former dry cleaner site, Floyd|Snider took over management of the existing remediation system to optimize performance, which helped to quickly reduce the mass of dissolved chlorinated volatile organic compounds and shorten the projected time frame for achievement of cleanup levels.
At a former machine shop site, Floyd|Snider assisted the City with reassessing a planned cleanup action with targeted supplemental data collection, resulting in a revised cleanup approach with lower cost and reduced impacts to public space that is equally protective of human health and the environment.
Our Approach
Our close coordination with Ecology and other regulatory agencies and strategic approach to data collection and analysis have advanced City properties toward cleanup and regulatory closure that were previously stalled in the regulatory process.
The Floyd|Snider Team has also supported the City of Bothell with outreach materials including factsheets for adjacent business owners, informational kiosks, and safety signage, all of which lead to improved community safety and project awareness.
Project Milestones
2019. Remedial Action completion on Lot P–South Site
2022. Final Consent Decree for Ultra Custom Care Cleaners Site remediation
2023. No Further Action Determination for Lot P–South Site
2025. Agreed Order Amendment for Riverside HVOC Site remediation
Our Approach
Floyd|Snider’s approach to contaminated site cleanup balances the City’s goals for downtown redevelopment, preservation of public spaces, and protection of human health and the environment. Our close coordination with Ecology and other regulatory agencies and strategic approach to data collection and analysis have advanced City properties toward cleanup and regulatory closure that were previously stalled in the regulatory process.
The Floyd|Snider Team has also supported the City of Bothell with outreach materials including factsheets for adjacent business owners, informational kiosks, and safety signage, all of which lead to improved community safety and project awareness.
Project Milestones
2019. Remedial Action completion on Lot P–South Site
2022. Final Consent Decree for Ultra Custom Care Cleaners Site remediation
2023. No Further Action Determination for Lot P–South Site
2025. Agreed Order Amendment for Riverside HVOC Site remediation